Civil Engineering Projects - Stormwater

Client
Lake County Department of Public Works
______

Location
Clermont,  Florida
_________

Key BCI Staff
Walter Reigner, PE, CPESC
Terry Dykehouse, PE
Terese Gregg, EI
Jeff Leahy
Brian Manley 

______

Project Costs
$100,000
______

Start Date
July 2006
______

Completion Date
Ongoing

Elbert Street Stormwater  Improvements

Scope

 Elbert Street Stormwater  Improvements

BCI was hired by Lake County to  improve water quality discharges to the Palatlakaha Chain of Lakes, particularly discharges to Lake Minnehaha. There is existing direct discharge from Elbert Street in  a residential area retrofit with French drains and a splash pool upstream of a wetland fringe on Lake Minnehaha.

BCI is providing the following for stormwater improvements:

  • Pollutant loading and pollutant reduction calculations
  • Resolution of Conflicting survey easements required, vacation of existing easements,  accommodating existing utilities, and saving existing trees 
  • Coordination with residents for design and location of retrofit system
  • Wetland delineation
  • French drain design
  • Pavement repair design
  • Plans preparation
  • Permitting through SJRWMD
  • Erosion and sediment control plan
  • Construction inspections
  • Cost estimating