Civil Engineering Projects -
Stormwater
|
|
Client
Seminole County
______
Location
Seminole County, Florida
__________
Key BCI Staff
Walter Reigner, PE, CPESC
Timothy Kelly, PE
Stephen Kuhn, PE
Jie Gao, EI
Thad Ellington
Eric Brown
______
Project Costs
$200,000
______
Start Date
August 2004
______
Completion Date
June 2005
|
Cassel Creek
Stormwater Evaluation
|
|
Scope
BCI, with assistance from CPH Engineers, evaluated this urbanized basin to determine the priority stormwater and groundwater pollutant loads to the Lake Howell system.
BCI tasks included the following:
-
Water quality monitoring to assess loads throughout system (storm event and base flow)
-
Sub-basin and in-stream pollutant loads estimations
-
Prioritization of sub-basins for load reduction
-
Assessment of relic wastewater treatment facility for water quality treatment
-
Conceptual load reduction
-
BMP development and cost estimations
-
Concept BMP plans development
|
|