h01 Logo Logo h03
BCI Engineers and Scientists
Print E-mail
Civil Engineering Projects - Stormwater

Client
Southwest Florida Water Management District
______

Location
Avon Park, Florida
______

Key BCI Staff
Walter Reigner, PE, CPESC
Timothy Kelly, PE
Michael Timpe, PE
Jie Gao, EI
Melissa Marshall, EI
______

Project Costs
$220,000
______

Start Date
2004
______

Completion Date
2006Â

Avon Park
Stormwater Master Plan

Scope

avonpark-01.jpgBCI was selected by the City of Avon Park to develop a stormwater utility that would serve to fund their stormwater program and enable the city to comply with state and federal legislative mandates such as NPDES and TMDL's. Immediately prior to this engagement, BCI was directed by the Southwest Florida Water Management District to develop a detailed citywide Stormwater Master Plan for the City of Avon Park.

The plan was developed based on the Water Management District's new guidelines and specifications for conducting watershed management plans. These guidelines were developed jointly by FEMA and the SWFWMD and require rigorous quality control and a high degree of correspondence between the GIS database/mapping element and the associated hydrologic model parameterization and connectivity.

 avonpark-02.jpg

 
< Prev   Next >
   
BCI Engineers & Scientists, Inc.  © 2007
Corporate Headquarters : 2000 E. Edgewood Dr., Suite 215, Lakeland, FL 33803 | 877-550-4224