GeoEnvironmental & Remediation Services Projects -
Contamination/Environmental
|
|
Client
Controlled Release Technology
______
Location
Clearwater, Florida
______
Key BCI Staff
Dennis Kenney, PG, CPG
Ralph Meder
______
Project Costs
$12,000
______
Start Date
June 2007
______
Completion Date
July 2007
|
Remedial Site Assessment
|
|
Scope
BCI was hired by Controlled Release Technologies, Inc. to prepare a Remedial Site Assessment Report for the Florida Department of Environmental Protection (FDEP) concerning a potentially hazardous contamination site.The contamination occurred as a result of a fire within an on-site warehouse. The fire ruptured some containers that were full of sodium hydroxide, which could have ultimately produced hazardous soil and groundwater contamination.
BCI performed on-site soil and groundwater analysis via hand augers and installed groundwater monitoring wells. The monitoring wells were evaluated for groundwater flow, water elevations, and specific water quality parameters.
A criteria analysis was performed to demonstrate the site chemistry results as they compare to the FDEP Soil and Groundwater Target Cleanup levels. The results showed the site was in regulatory limits.
|
|